how to hook UDF to a parallel job??
 
Hi,

I want to run a parallel job on a linux cluster. I have written a UDF which runs for my serial job. How do I make it useful for the same case to run in parallel. I am including my UDF below.

Any help would be appreciated!!


#include "udf.h"
DEFINE_PROPERTY(dyn_surf_tension, cell, thread)
{
double dst;
double t = CURRENT_TIME;
dst = 141121*pow(t,5) + 0.071;
return dst;
}